The paper proposes a novel planning approach for optimal sizing of standalone photovoltaic-wind-diesel-battery power supply for mobile telephony base stations. The approach is based on integration of a compr.
This paper presents the solution to utilizing a hybrid of photovoltaic (PV) solar and wind power system with a backup battery bank to provide feasibility and reliable electric power for a specific remote mobile base station located at west arise, Oromia.
... A hybrid system consisting of Photovoltaic modules and wind energy-based generators may be used to produce electricity for meeting power requirements of telecom towers (Acharya & Animesh, 2013; Yeshalem & Khan, 2017). A schematic of a PV-wind-batterybased hybrid system for electricity supply to telecom tower is shown in Fig. 17.
Monthly average electricity pro duction of PV/Battery hybrid system. 5.1.2. PV/Wind/Battery configuration are DC. The result is based upon the system w ith 41.4 kWh/day telecom load at 5.83 kWh/m solar radiation, 3.687m/s of wind speed and $0.8/L diesel price.
Solar and wind are available freely a nd thus appears to be a promising technology to provide reliable power supply in the remote areas and telecom industry of Ethiopia. The project aim generate and provide cost effective electric power to meet the BTS electric load requirement.
How much electricity does a DG/battery system consume?
the standalone diesel system consumes a total of 5,826 L/year and run for 5,884hr/year. The total shortage and zero unmet electric loads. CO2 emis sion is found to be 15,341 kg per year followed by 37.9 kg/year of CO emission per telecom tower. Figure 9. Monthly average electricity production of DG/Battery system.
All the necessary modeling, simulation, and techno-economic evaluation are carried out using Hybrid Optimization Model for Electric Renewable (HOMER) software. The best optimal system configurations namely PV/Battery and PV/Wind/Battery hybrid systems are compared with the conventional stand-alone diesel generator (DG) system.